Selasa, 20 November 2012

RENCANA ANGGARAN REHAB MASJID BROKOH


RENCANA ANGGARAN BIAYA
PEMBANGUNAN MASJID DESA BROKOH
TAHUN 2009






Desa
: Brokoh


Kecamatan : Wonotunggal

Kabupaten : Batang


Propinsi : Jawa Tengah







NO URAIAN SAT VOL HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN        
1 Air Kerja Is                 600.000,00             600.000,00
2 Alat Kerja Is               4.000.000,00           4.000.000,00
   SUB TOTAL I            4.600.000,00
II PEKERJAAN TANAH        
1 Galian Tanah m3 256.00                 12.000,00  3,072,000.00 
2 Uruga Tanah m3 62.00                   9.000,00  558,000.00 
3 Pas. Bt Kali 1 . 6 m3 56.70  263,057.20   14,915,343.24 
   SUB TOTAL II   18,545,343.24 
III PEKERJAAN PASANGAN        
1 Pas Bata 1 : 6 m2 642.00  53,215.00   34,164,030.00 
2 Plesteran 1 : 6 m2 1386.00  20,202.50   28,000,665.00 
3 Pas. Sloof 15/20 m3 14.60  3,368,905,29   49,186,017.23 
4 Fot plat m3 14.40  3,368,905.29   48,512,236.18 
5 Kolom 40/40 m3 40.69  3,368,905,29   137,080,756.25 
6 Balok Lantai 50/30 m3 31.35  3,368,905.29   105,615,180.84 
7 Plat Lantai 15 cm m3 36.10  3,368,905,29   121,617,480.97 
8 Balok Dag 20/35 m3 14.60  3,368,905,29   49,186,017.23 
9 Plat dag 10 cm m3 37.10  3,368,905,29   124,986,386.26 
10 Tangga m3 6.20  3,368,905,29   20,887,212.80 
11 Luifel 8 cm m3 8.22  3,368,905,29   27,692,401.48 
12 Kubah 12 cm m3 19.45  3,368,905,29   65,525,207.89 
   SUB TOTAL III   812,453,592.14 
IV PEKERJAAN PALFON        
1 Plafon Gipsum 9 mm + CAT m2 2.90  100,665.00   291,899.50 
2 Titik Lampu ttk 45.00  80,000.00   3,600,000.00 
3 Stop Kontak ttk 4.00  65,000.00   260,000.00 
4 MCB ttk 1.00  1,260,000.00   1,260,000.00 
   SUB TOTAL IV   5,411,899.50 
V PEKERJAAN LANTAI + ROSTER        
1 Lantai Keramik 60/60 m2 626  75,811.25   47,457,842.50 
2 Roster bh 48  17,500.00   840,000.00 
3 Pas. Lantai rabat 1 . 3 . 5 = 5 cm m2 162.00  32,598.75   5,280,997,50 
   SUB TOTAL V   53,578,840.00 
VI PEKERJAAN PINTU JENDELA        
1 Kosen kayu bengkirai m3 5.10             8.731.250,00         44.529.375,00
2 Daun pintu panil ky bengkirai m2 22.40               399.135,00           8.940.624,00
3 Daun jendela kaca bengkirai m2 12.28               342.150,00           4.201.602,00
4 Engsel jendela bh 64.00                   3.000,00             192.000,00
5 Grendel jendela bh 32.00                   4.000,00             128.000,00
6 Engsel pintu bh 30.00                   3.000,00               90.000,00
7 Kunci pinti bh 6.00                 60.000,00             360.000,00
8 kait angin bh 64.00                   3.000,00             192.000,00
9 Pas kaca m2 86.00  67,042.50            5.765.655,00
   SUB TOTAL VI              64.399.256
VII PEKERJAAN PENGECATAN + RAILING        
1 Cat Kayu m2 92.00  18,468.91   1,699,139.72 
2 Cat Dinding m2 1386.00  20,579.35   28,522,979.10 
3 Railing Tangga Besi 80 cm m' 53.70  485,000.00   26,044,500.00 
   SUB TOTAL VII   56,266,618.82 
 TOTAL   1,015,225,549.70 